This procedure describes the steps for configuring the prerequisites for installing System Center Operations Manager 2007 Reporting components.
Prerequisites
- Active Directory and DNS servers were installed and configured for the domain TECHREADY.RO
- Windows Server 2008 R2 with was installed on the server.
- The server was joined to the domain.
- Internet Information Services, ASP.NET, .NET Framework 2.0, .NET Framework 3.0, AJAX 1.0 and PowerShell were installed on the server.
- SQL Server 2008 with Reporting Services was installed
- Operations Manager 2007 R2 was installed on the server.
Installation and configuration steps
- Logon on the server using the domain Administrator acount.
- Launch the setup program for System Center Operations Manager 2007 R2.
- In the Start window select Install Operations Manager 2007 R2 Reporting.
- In the Welcome to Operations Manager 2007 R2 Reporting Setup window click Next.
- In the End-User License Agreement window select I accept the terms in the license agreement and click Next.
- In the Product Registration window enter the company details and click Next.
- In the Custom Setup window select both options and click Next.
- In the Prerequisite Check Passed window click Next.
- In the Connect to the Root Management Server window enter the name of the SCOM server and click Next.
- In the Connect to the Operations Manager Data Warehouse window verify the name of the SQL instance and click Next.
- In the Database and Log File Options window click Next.
- In the SQL Server Reporting Services Instance verify that the name of the SCOM server is selected and click Next.
- In the Data Warehouse Write Account window enter the credentials of the SCOMDWWrite account and click Next.
- In the Data Reader Account window enter the credentials of the SCOMDataReader account and click Next.
- In the Operational Data Reports window click Next.
- In The Microsoft Update window configure the update settings and click Next.
- In the Ready to Install the Program window click Install.
- In the Completing the Operations Manager Reporting Components Setup Wizard window click Finish.